Cause all that matters here is passing the PMI PMI-SP exam. Cause all that you need is a high score of PMI-SP PMI Scheduling Professional Practice Test exam. The only one thing you need to do is downloading Examcollection PMI-SP exam study guides now. We will not let you down with our money-back guarantee.

Q153. Which of the following statements best describes an activity in a project?

A. It is a defined set of functions a resource must complete for the project scope to be considered complete.

B. It is the effort needed to complete a work package.

C. It is the unit of resource utilization needed to complete a project deliverable.

D. It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Answer: B


Q154. CORRECT TEXT

Fill in the blank with an appropriate phrase.

The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

A. procurement SOW

Answer: A


Q155. Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

A. 48

B. 55

C. 54

D. 40

Answer: B


Q156. Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

A. Reports

B. Meetings

C. Diaries

D. Future planning

Answer: ABC


Q157. Once the project's WBS has been created what process may happen next?

A. Estimate activity resources

B. Define activities

C. Estimate activity durations

D. Sequence activities

Answer: B


Q158. You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

A. Cost variance report

B. Exceptions report

C. Performance management report

D. Schedule variance report

Answer: B


Q159. Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

A. Project calendar

B. Activity attributes

C. Resource calendar

D. Schedule management plan

Answer: A


Q160. Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

A. Project charter

B. Scope of statement

C. SOW

D. WBS

Answer: C