Q81. You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?

A. Parametric modeling

B. Analogous

C. Top-down

D. Bottom-up

Answer: D


Q82. You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

A. 1.02

B. 0.98

C. 0.90

D. -$108,120

Answer: C


Q83. You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

A. Project change control process

B. Perform integrated change control process

C. Configuration management

D. Communications management

Answer: B


Q84. Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?

A. Thomas

B. Sarah

C. Each of the team leaders for the eight virtual teams

D. Beth

Answer: D


Q85. Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the work that is remaining in the project. Alice, one of Gary's project team members, consistently reports that she's late on her project work. After the meeting, Gary and Alice discuss why the work is late as it is causing other delays in the project.

What is the review of the late work commonly called?

A. Variance analysis

B. Leadership

C. Quality control

D. Discipline

Answer: A


Q86. Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

A. People will behave based on what their behavior brings them.

B. As employees do repetitive tasks, duration should decrease.

C. Work expands to fill the amount of time allotted to it.

D. An exponential increase labor does not correlate to an exponential decrease in duration.

Answer: C


Q87. You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?

A. Project schedule

B. Work performance information

C. Project management plan

D. Earned value management results

Answer: D


Q88. In which of the following process groups does Integration Change Control Process fall?

A. Execution

B. Initiating

C. Planning

D. Monitoring and Controlling

Answer: D