Exam Code: PMI-SP (Practice Exam Latest Test Questions VCE PDF)
Exam Name: PMI Scheduling Professional Practice Test
Certification Provider: PMI
Free Today! Guaranteed Training- Pass PMI-SP Exam.
2021 Nov PMI-SP exam answers
Q141. You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?
A. The duration will increase, but the labor will stay the same.
B. The duration will decrease as new team members are brought onto the project.
C. Nothing, new resources will be incorporated into the project team.
D. The duration will increase, but the labor will decrease.
Answer: A
Q142. Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?
A. Project charter
B. Project scope statement
C. Project communications management plan
D. Resource calendar
Answer: D
Q143. You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?
A. Develop schedule
B. Estimate activity durations
C. Control schedule
D. Estimate activity resources
Answer: C
Q144. Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?
A. Communications management plan
B. Stakeholder register
C. Requirements
D. Stakeholder management strategy
Answer: B
Q145. Paula works as a project manager for her organization. She is working with the project team to define the activity attributes. Which of the following is NOT a valid activity attribute?
A. Activity Name
B. Activity ID
C. Risk event
D. WBS ID
Answer: C
Regenerate PMI-SP study guide:
Q146. Sam works as a project manager for BlueWell Inc. Which of the following processes will he use for selecting a scheduling method, scheduling tool, incorporating project specific data within that scheduling tool to develop a project specific schedule model, and generating project schedule?
A. Constructability Analysis process
B. Schedule Maintenance process
C. Schedule Development process
D. Perform Integrated Change Control process
Answer: C
Q147. Which of the following allows activities to be done in parallel that would normally be done in sequence?
A. Lag time
B. Lead time
C. Fast tracking
D. Crashing
Answer: C
Q148. You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is.
What value do you report?
A. -$135,000
B. .67
C. .81
D. -$65,000
Answer: C
Q149. The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
A. Activity list
B. Milestone list
C. Activity attributes
D. Project document updates
Answer: D
Q150. You are the project manager of a software development project. Your project team will be creating a webbased software application that will allow your company's customers to browse your website, search inventory, and place orders among other things. Your project team will, on a regular basis, need to update their computer virus prevention software, update their operating systems, and perform other maintenance on their computers in order to complete the project. This maintenance work is not directly tied to the project deliverables, but it is needed in order for the project to be completed. What term best describes this maintenance work?
A. Project management overhead
B. Discrete effort
C. Level of effort
D. Cost of conformance to quality
Answer: C